CUSTOM BARGE CUT PROPOSAL
WATERJET TA9 HEADER BARGEOJ INDUSTRIAL MAINTENANCESUNCOR BASE PLANT
Prepared for OJ Industrial Maintenance, this proposal for cutting mending plates on the TA9 Header Barge utilizing Innovative Well Abandonment’s custom-designed ultra-high-pressure (UHP) waterjet cutting system.
Compliant








01 — Project Area
SUNCOR BASE PLANT TAILINGS POND
OJ Industrial Maintenance
TAILINGS AREA 9
Innovative Well Abandonment has been contracted to cut the barge currently stationed on Tailings Area 9 into two distinct halves. The operation involves utilizing custom ultra-high-pressure (UHP) waterjet cutting technology to sever the mending plates along both sides of the barge.
02 — Rates
Equipment & Rate Schedule
Itemized project estimate showing the supplied units, quantities, rates and extended totals.
Primary Equipment
UHP CUTTING TRUCK OPERATIONS
$0.00$18,300.00
Mobilization, demobilization and two onsite days
Cutting Operations
Cut Truck Mobilization
Hourly × 06 at $0.00$425.00
$0.00$2,550.00
Cut Truck Demobilization
Hourly × 06 at $0.00$425.00
$0.00$2,550.00
Cutting Truck - Onsite Day #1
Hourly × 012 at $0.00$550.00
$0.00$6,600.00
Cutting Truck - Onsite Day #2
Hourly × 012 at $0.00$550.00
$0.00$6,600.00
Crew & Logistics
Project Manager
Hourly × 0.040.5 at $0.00$140.00
$0.00$5,670.00
Supervisor 1
Hourly × 0.040.5 at $0.00$120.00
$0.00$4,860.00
Operator 1
Hourly × 0.040.5 at $0.00$100.00
$0.00$4,050.00
Support Truck #1
Hourly × 0.040.5 at $0.00$25.00
$0.00$1,012.50
Support Truck Mobilization
KM × 0645 at $0.00$2.00
$0.00$1,290.00
Support Truck Demobilization
KM × 0645 at $0.00$2.00
$0.00$1,290.00
Project Support
Tooling
One time × 01 at $0.00$15,000.00
Estimated one-time tooling and machining cost as per discussion with Thomas Galliah. Actual will be billed.
$0.00$15,000.00
Prep & Design & Testing
Hourly × 024 at $0.00$140.00
$0.00$3,360.00
Estimated Project Total
Based on the units and quantities listed above.
$0.00$54,832.50
03 — Assumptions
Assumptions & Conditions
The basis of estimate for this proposal, including access, schedule and operating conditions.
Cut Direction
Innovative will use its custom track system to cut from the outside of the barge inward.
Working Platforms
OJ Industrial will provide platforms on both sides of the barge where the mending plates are being cut. Innovative will monitor and verify the cut as it progresses.
Welder
OJ Industrial will provide a welder to address any track-system mounting issues.
Temporary Power
Power—approximately a 2,000-watt generator—will be available on the barge for Innovative’s drive assembly.
Water-Jet Backing
Innovative will provide two 2×6 boards, eight feet long, inside the barge to prevent water-jet damage.
Barge Access
OJ Industrial will position the barge approximately 15–17 metres from shore so Innovative’s cutting truck can access it.
Accommodation
Pricing assumes Innovative employees will stay in camp accommodations provided at or near the Suncor Base Plant.
Safety and Communications
Suncor will provide any required gas-detection monitors and two-way communication devices.
04 — Contacts
Contacts & Next Steps
Leads on both sides of the project, and what has to close before the crew mobilizes.

OJ Industrial Maintenance
Address
1409 – 4th Street,Nisku, AB T9E 7M9
Innovative Well Abandonment
Address
11630 Kingsway NW,Edmonton, Albert T5G 0X5